For the purpose of this article, the words and phrases used herein shall have the meanings ascribed to them in this section, unless the context clearly indicates to the contrary.
(a) Approved shall mean approved by the chief building official, the electrical inspector or his or her designee.
(b) Authorized person shall mean any individual, firm or corporation who or which is licensed under the provisions of this article to do the work as permitted under the specified provisions of this article.
(c) City shall mean the territory within the corporate limits of this city.
(d) Conductor shall mean a wire or cable or other form of metal suitable for carrying the electric current or potential.
(e) Electrical construction or installation shall mean and include all work and materials used in installing, maintaining or extending a system of electrical wiring and all appurtenances, apparatus or equipment used in connection therewith, inside or attached to any building, structure, lot or premises, except industrial plants where fulltime maintenance is provided and other agencies providing inspections of installations and facilities. Electrical construction shall not be held to mean or include any of the following:
(1) The replacement of lamps, fuses, bulbs or the connection of portable electrical equipment to suitable permanently installed receptacles and replacement of receptacles and switches, lighting fixtures and apparatus where no changes or alterations are made to the wiring;
(2) Any work involved in the manufacturing, repair or testing of any electrical equipment or apparatus, but not including any permanent wiring; or
(3) Any work in industrial establishments where inspections come under the scope of other inspection agencies.
(f) Equipment shall mean conductors, materials, fittings, devices, appliances, fixtures, apparatus, motors and the like, used as a part of or in connection with an electrical installation.
(g) Inspector shall mean the chief building official or any individual who has been appointed by the city as electrical inspector.
(h) Person shall mean a natural person, his or her heirs, executors, administrators or assigns, and also includes a firm, partnership or corporation, its (,] or their successors, assigns, or the agent of any of the aforesaid.
(i) Special permission shall mean the written consent of the chief building official or the electrical inspector.
(j) Special ruling shall mean a written ruling filed in the office of the chief building official or the electrical inspector.
(Code 2000)
(a) The standard code known as the National Electrical Code of 2020, a publication of the National Fire Protection Association, the same being a standard code for the installation of electrical wiring and apparatus and available in book form is hereby incorporated by reference herein and made a part of this article as authorized and in the manner prescribed by K.S.A. 12-3009:3012. No fewer than three copies of the NFPA 70 shall be marked or stamped “Official Copy as Incorporated by the Code of the City of Goessel,” and shall be filed with the city clerk to be open to inspection and available to the public at all reasonable hours of business.
(b) Any person violating any provision of such code shall be punished as provided in section 1-116 of this code.
(Ord. 125, Sec. 3; Code 2000; Ord. 304)
The following sections of this article are in addition to the provisions of the standard code incorporated by reference in section 4-202.
(Code 2000)
The director of public works or his or her authorized designee shall be responsible for the administration and enforcement of this article and appointment of an electrical inspector in accordance with section 4-104 of this chapter, which shall apply in a like manner to this article.
(Ord. 125, Sec. 4; Code 2000)
The director of public works may assume the responsibilities of or the mayor may appoint some qualified officer or employee of the city to be and perform the duties of electrical inspector as may be required, subject to the consent and approval of the governing body.
(Ord. 125, Sec. 4; Code 2000)
The electrical inspector shall have the following duties:
(a) To enforce all regulations relating to electrical construction, alteration, repair or removal;
(b) May permit, with the approval of the governing body, on the basis of duly authenticated reports from recognized sources, the use of new materials or modes of electrical construction, not provided for in this article, and may, for the purpose of carrying out the intent of this article adopt an accepted standard of material or workmanlike practices of federal or state bureaus, national, technical organizations or fire underwriters;
(c) To examine all buildings requiring electrical construction in the process of erection, construction, alteration or relocation in the city for the purpose of determining whether the work is in compliance with the permit given and in compliance with the regulations of the city pertaining to such work, including zoning regulations; and
(d) To keep comprehensive records of applications, of permits or certificates issued, of inspections made, of reports rendered, and of notices or orders issued. All such records shall be open to public inspection during stated office hours, but shall not be removed from the office of the building official or electrical inspector without his or her written consent.
(Code 2000)
The electrical inspector shall have the following powers:
(a) To enter any building or structure or premises at any reasonable hour, whether complete or in the process of erection, to perform the duties contained in this chapter;
(b) To adopt and enforce all such prudent emergency measures as he or she may deem necessary and expedient for the public safety under the laws of the city;
(c) May cause any work done in violation of this chapter to be discontinued until he or she shall have satisfactory evidence that the work will be done in accordance with the electrical regulations of the city, subject to the right of any installer or owner to appeal to the governing body.
(Code 2000)
The electrical inspector, or his or her agent, upon proper identification, shall have authority to enter any building, structure or premises at any reasonable hour to perform his or her duties as set out in this chapter.
(Code 2000)
(a) The governing body shall be the final determiner of the scope and meaning of all provisions of the electrical code which may be unclear, ambiguous, or requiring interpretation.
(b) The electrical inspector shall have power to modify any of the provisions of the electrical code upon application in writing by the owner or lessee or his or her authorized agent, when there are practical difficulties in the way of carrying out the strict letter of the code. In approving modifications, the electrical inspector shall see that the spirit of the code is observed, public safety secured and substantial justice done. The particulars of a modification when granted or allowed and the decision of the inspector thereon shall be entered upon the records of the electrical inspector and a signed copy shall be furnished to the applicant.
(Code 2000)
Upon the completion of any electrical work covered by this article, it shall be the duty of the person doing such work to notify the electrical inspector and request that it be inspected; after which such work shall be inspected promptly as hereinafter provided.
(Code 2000)
(a) When any electric equipment is to be hidden from view by the permanent placement of parts of the building, the person, firm or corporation installing the equipment shall notify the building inspector and such equipment shall not be concealed until it has been inspected, approved or authorized by the electrical inspector or until 24 hours, exclusive of Saturdays, Sundays and holidays, shall have elapsed from the time of such notification. On large installations, where the concealment of equipment proceeds continuously, the person, firm or corporation installing the electrical equipment shall give the electrical inspector due notice and inspections shall be made periodically during the progress of the work.
(b) The electrical inspector shall have the authority to require building contractors to open such work which, in any manner, conceals electrical wiring that has been closed without his or her knowledge or permission, and in no case shall the inspector issue a certificate of approval until satisfied that the work is in accordance with the provisions of this article. The inspector shall also have the right to refuse to issue a certificate of approval on any wiring, that is concealed in such manner that it cannot be fully determined that it has been done in accordance with this article.
(Code 2000)
An initial inspection fee of $7, and an inspection fee of $7 for subsequent inspections required shall be paid before any electrical installation will be approved or a certificate of approval issued.
(Code 2000)
(a) When the electrical inspector finds an electrical construction or installation to be in conformity with the provisions of this article, he or she shall issue to the person, firm, or corporation performing the electrical construction work or making the installation, a certificate of approval, with duplicate copy for delivery to the owner, authorizing the use of the installation and connection to the supply of electricity.
(b) When a certificate of approval is issued authorizing the connection and use of a temporary installation, the certificate shall expire at a time to be stated therein and shall be revocable for cause by the electrical inspector.
(c) In no case shall certificates of approval be issued on electrical construction, installations or parts of installations where the work installed does not conform to the requirements of this article.
(d) If, upon inspection, the installation is not found to be fully in conformity with the provisions of this article, the electrical inspector shall immediately notify the person, firm, or corporation performing the electrical construction work or making the installation of the existing defects.
(e) No certificate of approval shall be issued unless the electric conductor or equipment has been installed in strict conformity with the provisions of this article and unless the electrical construction or installation is made in compliance with nationally approved methods of construction for safety to life and property as herein set forth.
(f) The electrical inspector shall be deemed the judge of whether the installation of electric conductors and equipment has been made in accordance with the requirements of this article.
(g) No certificate of approval shall be required for any of the following:
(1) The replacement of lamps, fuses, bulbs or the connection of portable electrical equipment to suitable permanently installed receptacles and replacement of receptacles and switches, lighting fixtures and apparatus where no changes or alterations are made to the wiring;
(2) Any work involved in the manufacturing, repair or testing of any electrical equipment or apparatus, but not including any permanent wiring; or
(3) Any work in industrial establishments where inspections come under the scope of other inspection agencies.
(Code 2000)
It shall be unlawful for any person, firm, or corporation to make connection to a supply of electricity to any building or electrical equipment for which an inspection is required, or which has been disconnected by the order of the electrical inspector, until a certificate of approval has been issued by the electrical inspector authorizing the connection and use of such electric supply. The electrical inspector may, at his or her discretion, authorize a temporary connection.
(Code 2000)
The electrical inspector shall periodically re-inspect existing installations of electrical conductors and equipment. When the installation of any conductors or equipment is found to be in a dangerous or unsafe condition, the person, firm, or corporation owning, using, or operating the installation shall be notified in writing and shall make the necessary repairs or changes required to place the conductors or equipment in safe condition and have the work completed within the period specified by the electrical inspector.
(Code 2000)
(a) If in the judgment of the electrical inspector, after an inspection, any electrical conductors, appliances or equipment in any building are unsafe or dangerous to persons or property, the inspector shall have the power to cause the wires or appliances to be disconnected from the source of electrical energy supplying these conductors or equipment, and may, at his or her discretion, seal the control switches for the same in an open or disconnected position, whereupon he or she shall give notice to the owner, or his or her agent, or by posting such notice at the site and shall also notify the utilities serving the premises. Thereafter, it shall be unlawful for any person to cause or permit electric current to be supplied to the electrical conductors, appliances or equipment so sealed until they shall have been made safe and the inspector shall have issued a certificate of approval to that effect.
(b) It shall be the duty of the electrical inspector to cause all dead wires, unused poles or electric apparatus on the outside of the buildings or in streets or alleys to be removed at the expense of the owners thereof by giving the owners written notice.
(c) When the electrical inspector condemns all or part of any electrical installation, the owner may, within 10 days after receiving written notice thereof, file a petition in writing for review of the action of the building inspector by the governing body, upon the receipt of which the governing body shall at once proceed to determine the facts, and within 10 days from receiving the petition make a decision in accordance with their findings.
(Code 2000)
It shall be unlawful for any unauthorized person to, in any manner, change or alter electrical conductors or equipment in or on any building. If in the course of the erection of a building or structure, electrical conductors or equipment are in such position as to interfere with the erection or completion of the structure, notice shall be immediately given the authorized person or firm installing the electrical conductors or equipment, and the needed change shall be made by such authorized person or firm.
(Code 2000)
Nothing herein contained shall prohibit any property owner from personally performing any electrical construction or installing electrical wiring or equipment within and upon his or her own residence and intended for his or her personal use and permanent occupancy; provided, the owner shall satisfy the electrical inspector as to his or her ability to perform such work or install such electrical wiring, secure a permit, pay required fees, do work in accordance with this article, and apply for an inspection and receive a certificate of approval. Personal electrical construction or installation performed by an owner under this section shall be by himself, herself, for himself or herself on his or her own residence, without compensation and no person shall be employed to assist him or her in any way on such work except an electrician or electrical contractor licensed by the city.
(Code 2000)
No electric materials for wiring of appliances or equipment shall be installed in the city unless they are in conformity with the provisions of this article and with the approved standards of construction for safety to life and property. Conformity of materials for wiring appliances and equipment to the standards of the Underwriters Laboratories, Inc. shall be prima facie evidence that the materials, devices, appliances and equipment comply with the requirements of this article.
(Code 2000)
This article shall not be construed to relieve from or lessen the responsibility or liability of any party owning, operating, controlling or installing any electrical equipment for damages to persons or property caused by any defect therein, nor shall the city be held as assuming any such liability, by reason of the inspection or re-inspection authorized herein, or the certificate of approval of any work or equipment authorized herein or by reason of any permit or license granted herein.
(Code 2000)
If any section of the National Electrical Code or of this article shall be held unconstitutional or otherwise invalid by any court of competent jurisdiction, then such section shall be considered separate and apart from the remaining provisions of the National Electrical Code or of this article, the section is to be completely severable from the remaining provisions which shall continue in full force and effect.
(Code 2000)